25LRR 1-52, LRR 1-53, URB 55 - USA - Installation & Operating Manual - 850703-00
Installing the LRR 1-52, LRR 1-53 conductivity controller
The LRR 1-52, LRR 1-53 conductivity controller snaps onto a TH 35 support rail in a control cabinet.
DANGER DANGER
There is a risk of electric shock during work on electrical systems.
Switch off the voltage to the plant before you install the equipment.
Check that the plant is not carrying live voltage before commencing work.
1. Switch off the voltage to the plant and secure any surrounding equipment in the control cabinet
that is live, so it cannot be touched.
2. Carefully press the unit onto the support rail until the holder clips into place.

Table of Contents

Other manuals for GESTRA LRR 1-52

Questions and Answers:

Question and Answer IconNeed help?

Do you have a question about the GESTRA LRR 1-52 and is the answer not in the manual?

GESTRA LRR 1-52 Specifications

General IconGeneral
BrandGESTRA
ModelLRR 1-52
CategoryController
LanguageEnglish

Related product manuals