Changing the equipment settings
DANGER DANGER
Danger of death from electric shock! Do not touch live connections on terminal
strips.
Always switch off the voltage to the equipment before performing work on the
terminal strips.
Check that the plant is not carrying live voltage before commencing work.
You can change the input and function of the LRR 1-52, LRR 1-53 conductivity controller at any
time if necessary using code switch D (see Fig. 19).
Make changes before installing the conductivity controller, when access is easier.
You will need the following tools:
Flat blade screwdriver, size 3/32in (2.4mm)
Pozidriv screwdriver, size PZ1
Proceed as follows:
1. Switch off the supply voltage to the equipment or plant.
2. Unscrew and pull off the lower terminal strip, see Fig. 8.
3. Set code switch D (see Fig. 19) as desired.
4. When your changes are complete, put the terminal strip back on and screw in place.

Table of Contents

Other manuals for GESTRA LRR 1-52

Questions and Answers:

Question and Answer IconNeed help?

Do you have a question about the GESTRA LRR 1-52 and is the answer not in the manual?

GESTRA LRR 1-52 Specifications

General IconGeneral
BrandGESTRA
ModelLRR 1-52
CategoryController
LanguageEnglish

Related product manuals