10. Install all removed components on the new system board.
11. If removed, install the air baffle.
12. Install the access panel.
13. Do one of the following:
Orient the server back in tower mode.
Install the server into the rack.
14. Connect all peripheral cables to the server.
15. Connect each power cord to the server.
16. Connect each power cord to the power source.
17. Power up the server .
18. Make sure all firmware, including option cards and embedded devices, is updated to the same versions to ensure that the latest