Removal and replacement procedures 102
Rail kit
WARNING: To reduce the risk of personal injury from hot surfaces, allow the drives and the
internal system components to cool before touching them.
NOTE: The images below are for reference only; the actual product may vary.
To install the component:
1. Power down the server (on page 20).
2. Disconnect all peripheral cables from the server.
3. Before installation check the rack post type used, as the rail kit is pre-installed with screws for for
square hole posts. If the rack post type features round hole posts, please switch the pre-installed
square hole screws, and then install round hole screws as seen in the image below.