Operations 20
Operations
Power down the server
Before powering down the server for any upgrade or maintenance procedures, perform a backup of
critical server data and programs.
IMPORTANT: When the server is in standby mode, auxiliary power is still being provided to
the system.
To power down the server, use one of the following methods:
Press and release the Power On/Standby button.
This method initiates a controlled shutdown of applications and the OS before the server enters
standby mode.
Press and hold the Power On/Standby button for more than 4 seconds to force the server to enter
standby mode.
This method forces the server to enter standby mode without properly exiting applications and the
OS. If an application stops responding, you can use this method to force a shutdown.
Use a virtual power button selection through BMC.
This method initiates a controlled remote shutdown of applications and the OS before the server
enters standby mode.
Before proceeding, verify that the server is in standby mode by observing that the system power LED is
amber.
Using Power Control function through BMC
The following options are available when using Power Control function through BMC:
Power OnSimilar to press and release of the Power On/Standby button.
Power OffSimilar to the press and hold of the Power On/Standby button more than 4 seconds.
Power CyclePower off and then power on the server.
Hard ResetA forced reboot that does not reach standby.