9. Route the energy pack cable as shown in below illustration.
10.
Connect the storage controller backup power cable.
11.
Install the air bale.
12. If removed, install the secondary riser cage.
13.
Install the access panel.
14. Install the server into the rack.
15. Connect all peripheral cables to the server.
16. Connect each power cord to the server.
17. Connect each power cord to the power source.
18.
Power up the server.
19. If removed,
install the front bezel.