Installing a rear 2SFF SAS/SATA drive cage over the power supplies
Prerequisites
Before you perform this procedure, make sure that you have the following items available:
• T-10 Torx screwdriver
• The components included with the hardware option kit
• The front bays are fully populated with 12 LFF or 24 SFF drives
• High performance fans are installed in all fan bays
Procedure
1. Power down the server.
2. Remove all power:
a. Disconnect each power cord from the power source.
b. Disconnect each power cord from the server.
3. Do one of the following:
•
Extend the server from the rack.
• Remove the server from the rack .
4. Remove the access panel.
5. Do one of the following:
If installed, remove the secondary riser cage.
Remove the secondary wall blank.
Hardware options installation 107