No. Check Item Acceptance Criteria
2 Cables routing Cables are routed properly as required
by the customer.
3 Cable tie Cable ties are evenly distributed and no
burr exists.
4 Grounding The PE cable is connected correctly,
securely, and reliably.
5 Switch The DC switch and all switches
connected to the battery are OFF.
6 Cable connection The AC output power cable, DC input
power cable, battery cable, and signal
cable are connected correctly, securely,
and reliably.
7 Unused terminal and port Unused terminals and ports are locked
by watertight caps.
8 Installation environment The installation space is proper, and
the installation environment is clean
and tidy.
7.2 System Power-On
● Power on the LUNA2000 within 24 hours after unpacking. The power-o time
cannot exceed 24 hours during maintenance.
● After turning on the battery switch, power on the inverter. For details about
how to power on the inverter, see the quick guide for the corresponding
inverter model.
If no PV module is congured, press the black start button rst.
Turn on the DC switch on the battery. After the battery is installed and powered
on for the rst time, the ring LED blinks for three circles. Observe the battery
indicator to check the running status.
LUNA2000-(5-30)-S0
User Manual 7 System Commissioning
Issue 15 (2024-01-12) Copyright © Huawei Digital Power Technologies Co., Ltd. 98