VM Series Maintenance and Safety Manual 704-0212-209 Operation Requirements 2- 5
Initial Test and Examination
Follow the instructions below for performing the initial test and examination of the
machine and its guarding system.
Arrange for a Hurco-certified Service Engineer to perform the final machine setup.
Complete these procedures prior to the arrival of the Service Engineer:
1. Provide utilities to the machine.
2. Check all machine lubrication levels.
3. Place the flood coolant tank, tubing, and coolant pump motor near the
machine base.
The Hurco-certified Service Engineer performs these tasks:
1. Inspects the machine level and makes required adjustments.
2. Checks and connects electrical service to the machine.
3. Installs the control console.
4. Measures voltages in the electrical cabinet and control enclosure and makes
adjustments, if needed.
5. Installs the flood coolant tank, tubing, and coolant pump motor.
6. Installs covers and enclosures.
7. Checks fans and pumps for proper operation.
8. Checks all axes for calibration and correct limit switch operation.
9. Tests the disk drive.
Hurco is not responsible for failures of the motor encoder and cable
assemblies resulting from abuse and direct spray of coolant.