EasyManua.ls Logo

Immergas AUDAX PRO 4 V2 - 14 Final Inspections and Test Operation; Inspection Prior to Test Operation; Test Operation

Immergas AUDAX PRO 4 V2
52 pages
Print Icon
To Next Page IconTo Next Page
To Next Page IconTo Next Page
To Previous Page IconTo Previous Page
To Previous Page IconTo Previous Page
Loading...
65 66
AUDAX PRO 4 V2 - AUDAX PRO 6 V2 AUDAX PRO 9 V2
50
14
FINAL INSPECTIONS
AND TEST OPERATION.
14.1 INSPECTION PRIOR TO TEST OPERATION.
1. Check the power cable and the communication cable of the
indoor unit and outdoor unit.
2. Check the supply voltage between the outdoor unit and the
electric panel.
- Check the voltage at 220-240 V ac ~ using a voltmeter.
3. Once the outdoor unit has been switched on, perform moni-
toring to verify that the indoor unit is connected and check the
options.
14.2 TEST OPERATION.
1. Run the unit by means of the indoor unit.
- Check the sound of the compressor during initial operation. Stop
it if it makes a screeching noise.
2. Check the operating status of the indoor and outdoor units
- Anomalous operating noise of the indoor and outdoor unit.
- Correct drainage of the indoor unit in cooling mode.
3. End of the test.
4. Explain to the customer how to use the condensing unit
following the user manual.

Table of Contents

Related product manuals