2. Apply new sealant to the leading 3 to 4 threads of the pipe plug.
Note: Itron recommends RectorSeal #5 sealant.
3. Using a 3/16" hand-driven Allen wrench, begin tightening the pipe plug into the threads,
using care not to cross-thread or remove the sealant during the process.
4. Tighten the pipe plug. Do not exceed 50 inch-pounds torque (5.6 Newton Meters).
5. Leak test following your utility's leak test procedure.
11 December 2019 TDC-1782-005 19
Intelis Gas Meter Installation Guide 3 Installation