ACU-SHIELD ROOF COATING *
* Provided with ship loose items in fan section (see table in Section, "Receiving & Inspection").
CAULKING (PROVIDED)
ROOF
HOUSING SPLIT
3" MIN



1. The mechanical joint between sections must be bolted and
sealed with polyurethane caulking.
2. Acu-Shield Roof Coating can be applied after polyurethane
caulking is dry and when surface temperature is between 45°F
and 108°F. Below 45°F, extra steps must be taken to keep
the polyurethane caulking, Acu-Shield, and metal reconnect
surfaces heated for proper application during installation.
Contact Product Service for further direction.
3. Do not apply when inclement weather is imminent within
a 24 hour period.
4. Do not apply to wet, ice, or snow covered surfaces.
5. Before applying, clean surface with wire brush or solvent
wipe (not provided).
6. Apply Acu-Shield Roof Coating with 3 inch wide roller or
3 inch wide paintbrush (not provided).
7. One quart applied at 45 mils is equal to a 3 inch wide X
33 foot long section.
8. Cure time will vary with temperature and humidity. Under
normal conditions, a rubber coating can be expected within
a 24 hour period.