6 Commissioning/Start-up/Shutdown
31 of 64
Etaline
CAUTION
Abnormal noises, vibrations, temperatures or leakage
Damage to the pump!
▷ Switch off the pump (set) immediately.
▷ Eliminate the causes before returning the pump set to service.
ü The system piping has been cleaned.
ü The pump, suction line and inlet tank, if any, have been vented and primed with
the fluid to be pumped.
ü The lines for priming and venting have been closed.
CAUTION
Start-up against open discharge line
Motor overload!
▷ Make sure the motor has sufficient power reserves.
▷ Use a soft starter.
▷ Use speed control.
1. Fully open the shut-off element in the suction head/suction lift line.
2. Close or slightly open the shut-off element in the discharge line.
3. Start up the motor.
4. Immediately after the pump has reached full rotational speed, slowly open the
shut-off element in the discharge line and adjust it to comply with the duty
point.
6.1.6 Shutdown
CAUTION
Heat build-up inside the pump
Damage to the shaft seal!
▷ Depending on the type of installation, the pump set requires sufficient after-
run time – with the heat source switched off – until the fluid handled has
cooled down.
CAUTION
Backflow of fluid handled is not permitted
Motor or winding damage! Mechanical seal damage!
▷ Close the shut-off elements.
ü The shut-off element in the suction line is and remains open.
1. Close the shut-off element in the discharge line.
2. Switch off the motor and make sure the pump set runs down smoothly to a
standstill.
NOTE
If the discharge line is equipped with a non-return or check valve, the shut-off
element may remain open provided that the system conditions and system
regulations are considered and observed.