Chapter 4 System Power-On Commissioning 27
Liebert CRV+ Series Air Conditioner User Manual
Observe the compressor suction pipes and make sure there is no water condensing on the surface of the compressor
and the pipes, so as to avoid the risk of slugging the compressor.
The unit discharging overheating degree is within 25°C ~ 50°C.
4.2.3 Inspection After Commissioning
After commissioning, confirm the items listed in Table 4-1.
Table 4-1 Inspection after commissioning
Check item Result
Check that all output functions are automatic
Check that the temperature & humidity settings and control
precisions are set reasonable
Make sure all the other functions are set reasonable