Installation, commissioning
Conducting an inspection after commissioning
7.6 Conducting an inspection after commissioning
Proceed as follows to conduct the inspection after commissioning.
Prerequisites These prerequisites must be fulfilled:
The machine is ready for operation.
Carrying out an in-
spection
Here's how to carry out an inspection:
Check all tapes and belts to make sure they run centered and have the
necessary tension.
If required, readjust these.
See Maintenance chapter.
The inspection has been carried out.
20 operating hours after the commissioning, it is necessary to perform
an inspection of all belts and tapes.