60
Before switching on the unit, read following 
recommendations:
The installer is obliged to verify correct operation of unit 
after installation.
11 TEST RUN AND FINAL 
    CHECKS
11.1 Final checks
When  the  complete  installation  and  all necessary 
settings have been carried out, close all front panels 
of the unit and refit the unit cover.
The service panel of the switch box may only be 
opened by a licensed electrician for maintenance 
purposes.
If required, the installer can perform a manual test run 
operation at any time to check correct operation of air 
purge, heating, cooling and domestic water heating, refer 
to 10.6.11 “Test run”.
11.2 Test run operation (manually)
That during the first running period of the unit, 
required power input may be higher than stated 
on the nameplate of the unit. This phenomenon 
originates from the compressor that needs 
elapse of a 50 hours run in period before 
reaching smooth operation and stable power 
consumption.
NOTE
In order to ensure optimal availability of the unit, a number 
of checks and inspections on the unit and the field wiring 
have to be carried out at regular intervals.
This maintenance needs to be carried out by your local 
technician.
In order to ensure optimal availability of the unit, a number 
of checks and inspections on the unit and the field wiring 
have to be carried out at regular intervals.
This maintenance has to be carried out by your local 
technician.
12 MAINTENANCE AND 
  SERVICE
DANGER
ELECTRIC SHOCK
Before carrying out any maintenance or 
repairing activity, must switch off the power 
supply on the supply panel.
Do not touch any live part for 10 minutes after 
the power supply is turned off.
The crank heater of compressor may operate 
even in standby.
Please note that some sections of the electric 
component box are hot.
Forbid touch any conductive parts.
Forbid rinse the unit. It may cause electric 
shock or fire.
Forbid leave the unit unattended when 
service panel is removed.
Make sure that the disposal of the glycol solution is done 
in accordance with relevant local laws and regulations.
Water pressure
Check the water pressure, if it is below 1 bar,fill water 
to the system.
Water filter
Clean the water filter.
Water pressure relief valve
Check for correct operation of the pressure relief 
valve by turning the black knob on the valve 
counter-clockWise:
-If you do not hear a clacking sound, contact your 
local dealer.
-In case the water keeps running out of the unit, close 
both the water inlet and outlet shut-off valves first and 
then contact your local dealer.
Pressure relief valve hose
Check that the pressure relief valve hose is 
positioned appropriately to drain the water.
Backup heater vessel insulation cover
Check that the backup heater insulation cover is 
fastened tightly around the backup heater vessel.
Domestic hot water tank pressure relief valve (field 
supply) Applies only to installations with a domestic 
hot water tank. Check for correct operation of the 
pressure relief valve on the domestic hot water tank.
Domestic hot water tank booster heater
Applies only to installations with a domestic hot water 
tank. It is advisable to remove lime buildup on the 
booster heater to extend its life span, especially in 
regions with hard water. To do so, drain the domestic 
hot water tank, remove the booster heater from the 
domestic hot water tank and immerse in a bucket (or 
similar) with lime-removing product for 24 hours.
Unit switch box
-Carry out a thorough visual inspection of the switch 
box and look for obvious defects such as loose 
connections or defective wiring.
-Check for correct operation of contactors with an 
ohm meter. All contacts of these contactors must be 
in open position.
Use of glycol (Refer to 9.4.4 "Water circuit anti-freeze 
protection") Document the glycol concentration and 
the pH-value in the system at least once a year.
-A PH-value below 8.0 indicates that a significant 
portion of the inhibitor has been depleted and that 
more inhibitor needs to be added.
-When the PH-value is below 7.0 then oxidation of the 
glycol occurred, the system should be drained and 
flushed thoroughly before severe damage occurs. 
The following checks must be performed at least once a 
year by qualified person.