Transport
VVM 310 should be transported and stored vertically
in a dry place. The VVM 310 may, however, be carefully
laid on its back when being moved into a building.
R
0
R
0
Assembly
႑
Position VVM 310 on a firm base that can take the
weight, preferably on a concrete floor or foundation.
Use the product's adjustable feet to obtain a horizont-
al and stable set-up.
30 - 50 mm
႑
The area where VVM 310 is located must be
equipped with floor drainage.
Installation area
Leave a space of 500 mm in front of the product. All
service on VVM 310 can be carried out from the front.
500
NOTE
Leave 10-25 mm free space between the in-
door module and the wall behind for routing
of cables and pipes.
5Chapter 2 | Delivery and handlingNIBE™ VVM 310
2 Delivery and handling