Chapter3 • Site Preparation 55
3
♦♦♦C H A P T E R  3
Site Preparation
This chapter describes the tasks you must complete before installing Oracle Database Appliance
into a rack and cabling it.
Preparing Your Site
Use the following procedure to prepare your site for Oracle Database Appliance installation:
Prepare Your Site
1.
Ensure that your site meets the environmental requirements in “Environmental
Specifications” on page 51.
2.
Ensure that your site meets the electrical specifications in “Electrical
Specifications” on page 50.
3.
Ensure that your site has adequate clearance for the shipping containers.
4.
Allow the equipment to acclimatize to the computer center environment.
If significant temperature differences exist (> 10
°
C / 18
°
F) between the new system and the
designated computer center, the equipment should be left in its boxes for a sufficient period of
time to allow the temperature of the equipment to come to within a few degrees of the computer
center.
Caution - Equipment damage. The system should never be powered on unless it is within the
supported operating range (temperature and humidity).
5.
Open the shipping containers.
You should do this at the location where the system will be installed, but outside of the
computer center itself.

Table of Contents

Other manuals for Oracle Database Appliance X6-2-HA

Questions and Answers:

Question and Answer IconNeed help?

Do you have a question about the Oracle Database Appliance X6-2-HA and is the answer not in the manual?

Oracle Database Appliance X6-2-HA Specifications

General IconGeneral
BrandOracle
ModelDatabase Appliance X6-2-HA
CategoryStorage
LanguageEnglish

Related product manuals