7.5 - PROPER COMMISSIONING CHECK
Check the connections made during the installation of the equipment (refer to chapter 6 “Installation”) for proper sealing
through a foaming solution (or equivalent control system).
7.6 - RESET OF SAFETY DEVICES AFTER COMMISSIONING
HAZARD!
Before resetting the safety devices, eliminate the causes that caused them to trip.
ATTENTION!
The maximum pressure slam-shut device is not reset if overpressure has not been eliminated in the
network, downstream of the gearbox.
The excess ow lock-up device will not reset if the fault has not been eliminated on the network.
NOTE!
While resetting the safety devices, the relief valve can temporarily trip.