LOW-PRESSURE GAS REGULATOR | COMMISSIONING | REV. 00
Use, maintenance and warning manual
7.7.2 - DRUM FIXED ON THE SECOND STAGE CONTROL HEAD
NOTE!
The drum must always be in a horizontal position with the camera facing the ground.
After commissioning the equipment (see paragraph 7.4), proceed as indicated in Tab. 7.41.:
Step Action
1 Unscrew the buttery screw (1) anticlockwise, making sure that the O-ring (2) remains in its seat.
2 Screw the brass tting (5) onto the regulator lid.
3
Fit the drum (3) to the brass tting (5) so that the rubber tube (4) of the regulator vent is in a vertical position
inside the drum itself.
4 Turn the buttery screw (1) clockwise, tightening it fully to ensure locking and sealing of the system.
5 Make sure the drum (3) is in a horizontal position.
Tab. 7.41.
Fig. 7.16. Drum xed on the second stage control head (underground regulator)

Table of Contents

Questions and Answers:

Question and Answer IconNeed help?

Do you have a question about the PIETRO FIORENTINI FE Series and is the answer not in the manual?

PIETRO FIORENTINI FE Series Specifications

General IconGeneral
BrandPIETRO FIORENTINI
ModelFE Series
CategoryController
LanguageEnglish

Related product manuals