EasyManua.ls Logo

Potterton Paramount four - 7.3 Commissioning procedure; 7.4 Gas settings

Potterton Paramount four
144 pages
Print Icon
To Next Page IconTo Next Page
To Next Page IconTo Next Page
To Previous Page IconTo Previous Page
To Previous Page IconTo Previous Page
Loading...
Only components tested and marked according to the respective standard have been used.
All system components have been installed according to the instruction of the manufacturers.
The whole system conforms to the standard.
To ensure the heat source operates reliably and economically for a long period, we recom
mend annual maintenance for the heat generator.
Date /signature
Company stamp
...............................
7.3 Commissioning procedure
7.3.1 Commissioning menu
The commissioning menu will be shown once during initial commissioning.
1. Change Language must be selected and confirmed with the OK but
ton.
2. Year select year and confirm.
3. Set time and date set and confirm.
4. Conclude by pressing the OK button.
Note
If the commissioning menu entry is terminated by pressing ESC,
the menu will be shown again next time the appliance is switched
on.
7.4
Gas settings
7.4.1 Factory settings
The Paramount four has been set to the nominal heat load by the manu
facturer.
Gas type G20 (natural gas G20 with Wobbe index W
oN
= 15.0 kWh/m
3
)
The specific set gas type can be seen on the optional label glued to the
burner. The factory setting data must be checked against the on-site sup
ply conditions before installation of the Paramount four.
7.4.2 Supply pressure
The supply pressure must be between the values given in the technical
data table (see reference below).
The connecting pressure is measured as pressure in the gas flow at the
measuring nozzle of the gas valve.
Danger
The Paramount four must not be started up when the supply pres
sures are outside the said range.
The gas supply company must be informed.
For more information, see
Technical data, page 14
Technical data, page 0
Gas valve, page 0
Gas valve, page 47
7.4.3 CO
2
content
The CO
2
content in the exhaust gas must be checked during commission
ing and during regular maintenance of the boiler, as well as after recon
struction work on the boiler or on the exhaust gas system.
CO
2
content during operation see section
Technical data
.
RA-0000065
7 Commissioning
7658013 - 02 - 15092016 Paramount four 30 – 115 kW 45

Table of Contents

Related product manuals