Liberty 100 Smart Electricity Meter Technical Reference Manual
Manual Display in Default Mode
(timeout 2 secs)
Followed by value
(timeout 4 secs)
Press key 0 to advance to the next display.
In the example the date in the meter is 1st June
2012.
Title 4: Current load
(timeout 2 secs)
Followed by value
Or
Or
Or
(timeout 4 secs)
Press key 0 to return to the 1
st
display.
Press key B to scroll back up the display list.
No key press at the end of this display sequence will
cause the auto-cycle display to resume.
The 4
th
set displays the current load and its status.
The examples indicate the following:
The current load 10.15 kW is in-between the low and
high active import power thresholds.
The current load 2.15 kW is below the low active
import power threshold.
The current load 22.15 kW is above the high active
import power threshold.
24.10 kW is the power currently being exported.
Table 28: Key '0' display in Default mode (once the meter is commissioned)
If commissioning is not performed in the meter then a short press of key ‘0’ will display the following indicating