EasyManuals Logo

Siemens SIPROTEC 7SJ62 User Manual

Siemens SIPROTEC 7SJ62
704 pages
To Next Page IconTo Next Page
To Next Page IconTo Next Page
To Previous Page IconTo Previous Page
To Previous Page IconTo Previous Page
Page #226 background imageLoading...
Page #226 background image
Functions
2.12 Ground Fault Protection 64, 67N(s), 50N(s), 51N(s)
SIPROTEC, 7SJ62/64, Manual
C53000-G1140-C207-2, Release date 01.2008
226
2.12.2 Ground Fault Detection for U0/I0-ϕ Measurement
Voltage Element
The voltage element relies on a pickup initiated by the displacement voltage V
0
or 3 · V
0
. Additionally, the faulty
phase is determined. The displacement voltage V
0
can be directly applied to the device, or the summary
voltage 3 · V
0
can be calculated by the device based on the three phase–to–ground voltages. In the latter case,
the three voltage inputs must be connected to voltage transformers in a grounded-wye configuration (see also
address 213 VT Connect. 3ph in Subsection 2.1.3). If the device is only provided with phase-to-phase volt-
ages, it is not possible to calculate a displacement voltage from them. In this case the direction cannot be de-
termined.
If the displacement voltage is calculated, then:
3 · V
0
= V
A
+ V
B
+ V
C
If the displacement voltage is directly applied to the device, then V
0
is the voltage at the device terminals. It is
not affected by parameter Vph / Vdelta (address 206).
Pickup performed by the displacement voltage can be delayed (64-1 DELAY) for tripping.
It is important to note that the total trip-command time then consists of the displacement voltage measurement
time (about 50 ms) plus the pickup delay time 64-1 DELAY.
After the voltage element picks up due to detection of a displacement voltage, the grounded phase is identified,
if possible. To do this, the individual phase-to-ground voltages are measured. Of course, this is only possible if
three phase-to-ground voltages are obtained from voltage transformers connected in a grounded wye config-
uration. If the voltage magnitude for any given phase is below the setting value V
Ph min
, that phase is detected
as the grounded phase as long as the remaining phase-to-ground voltages are simultaneously above the
setting value V
Ph max
.
Figure 2-82 Determination of Ground-faulted Phase
www . ElectricalPartManuals . com

Table of Contents

Other manuals for Siemens SIPROTEC 7SJ62

Questions and Answers:

Question and Answer IconNeed help?

Do you have a question about the Siemens SIPROTEC 7SJ62 and is the answer not in the manual?

Siemens SIPROTEC 7SJ62 Specifications

General IconGeneral
BrandSiemens
ModelSIPROTEC 7SJ62
CategoryRelays
LanguageEnglish

Related product manuals