EasyManua.ls Logo

Siemens ST950 - Solar Cell Testing; Junction System Testing; Lamp Supply Transformer; Site Information Export (PI Dump)

Siemens ST950
154 pages
To Next Page IconTo Next Page
To Next Page IconTo Next Page
To Previous Page IconTo Previous Page
To Previous Page IconTo Previous Page
Loading...
Mobility, Intelligent Traffic Systems
Sopers Lane, Poole, Dorset, BH17 7ER
Security classification
Unrestricted
Page
111 of 154
Version
7
Status
Issued
Last Editor
manpreet.jeerh
Date
January 2020
Document Name
ST950 ICM Handbook
Document No.
667/HE/45950/000
The 'Learning Assist' feature can be enabled from the web page:
Status and Configuration Controller LMU Reset/Learning
During the learning sequence, the percentage complete status for each signal can
be monitored on the web page:
Status and Configuration Controller LMU Readings
The RS232 handset can also be used to learn the lamp loads using the handset
commands 'KRD' and 'KLR'.
7.4.11 Solar Cell Testing
For this test to be performed the ambient light conditions must be
sufficient to set the bright condition on the controller.
Correct operation of the solar cell can be checked by covering the solar cell for at
least one minute and checking that the controller (suitably configured to allow
dimming) dims the signals. Remove the cover and check that the signals return to
the bright condition.
Use with Care!
Dim signals may be difficult for road users to see during daylight hours
7.4.12 Junction System Testing
Using the detect lights on the above ground detectors, ensure that all above ground
detectors (Kerbside and On-Crossing) are functional and have the required zone of
detection.
Using the web page:
Status and Configuration Controller I/O Lines
Or the Handset command “IOP”, check that all road detector loops, Above Ground
Detector demand pushbuttons etc are correctly connected.
Clear all faults in the log and allow the junction to run normally. Periodically check
the fault table / system log and ensure that no faults are raised. Verify that the
controller has the correct date and time and is keeping correct time.
7.4.13 Lamp Supply Transformer
Measure the incoming mains voltage and wire the transformer.
7.4.14 Site Information Export (PI dump)
Various configuration and status information can be exported from the controller to
be reviewed and stored using the 'Export Site Information' button on the System
web page. This can be used to collect information as part of a periodic inspection
(sometimes referred to as a 'PI dump').
Press the 'Export Site Information' button to download a zip file containing all of the
site information. The filename generated is based on the following: