SMA Solar Technology AG 7 Commissioning
Installation Manual SI80H-60H-OffGrid-IA-en-11 85
10. Setting the three-phase off-grid system:
• Select the 003.15 ClstType parameter and
press the button.
•Set 3Phs and press the button.
• Confirm the three-phase off-grid system with Y.
11. Setting multicluster operation:
• Select the 003.16 Sys parameter and press the
button.
•Set MultiClst and press the button.
• Confirm multicluster operation with Y.
12. Setting the cluster for a main cluster:
• Select the 003.17 ClstMod parameter and
press the button.
•Set MainClst and press the button.
• Confirm the type of the cluster with Y.
• Continue with step 14.