SUNSYNK MAX | Installer Manual52
Zero Export + Limit To Load Only: The hybrid inverter will only provide power to the backup load connect-
ed. The hybrid inverter will neither provide power to the home load nor sell power to the grid. The built-in CT
will detect power owing back to the grid and will reduce the power of the inverter only to supply the local
load and charge the battery.
ZeroExport: The hybrid inverter will not only provide power to the backup load connected but also give
power to the home load connected. If PV power and battery power are insucient, it will take grid energy
as a supplement. The hybrid inverter will not sell power to the grid. In this mode, a CT is needed. For the
installation method of the CT, please refer to the chapter "CT Connection". The external CT will detect power
owing back to the grid and will reduce the power of the inverter only to supply the local load, charge the
battery, and home load.
GridBackup Load On-Grid Home Load
Battery
Solar
GridBackup Load On-Grid Home Load
Battery
Solar
CT
Set a real time to start and stop charging or discharging the battery.
Choose to charge the battery from the grid or generator.
Limit export power to the grid.
Set the unit to charge the battery from the grid or generator ticking ‘Grid’ or ‘Gen’ and set what times this
needs to occur.
Set the time to discharge the unit to the load or export to the grid by unticking ‘Grid’ and ‘Gen’.
If nothing ticked: This Mode allows the hybrid inverter to sell back any excess power produced by the solar
panels to the grid. If the use time is active, the battery energy can also be sold into the grid. The PV energy
will be used to power the load and charge the battery, and then excess energy will ow to the grid. Power
source priority for the load is as follows:
1. Solar Panels.
2. Grid.
3. Batteries (until programmable % discharge is reached).
What you can do from this page:

Table of Contents

Questions and Answers:

Question and Answer IconNeed help?

Do you have a question about the SunSynk SYNK-16K-SG01LP1 and is the answer not in the manual?

SunSynk SYNK-16K-SG01LP1 Specifications

General IconGeneral
BrandSunSynk
ModelSYNK-16K-SG01LP1
CategoryInverter
LanguageEnglish

Related product manuals