3–4
ASPHALT SURFACE PREPARATION
Test site selection for asphalt surfaces is much the same as soils except that
preparation differs slightly. Voids may be filled on coarse, open-graded
mixes using soft sand or cement powder, taking care to fill only the voids
and leaving the asphalt bare for surface contact with the gauge base. The
base should be resting on the asphalt and not on the fill material.
Try to “rock” the gauge – if you can “rock” it, place more fill material or
move the gauge to a flatter surface to correct the problem; the gauge should
not rock. Put the source rod in backscatter position, making sure the rod is
in the proper index rod notch and not resting on the asphalt.

Table of Contents

Other manuals for Troxler 3440

Questions and Answers:

Question and Answer IconNeed help?

Do you have a question about the Troxler 3440 and is the answer not in the manual?

Troxler 3440 Specifications

General IconGeneral
Model3440
CategoryMeasuring Instruments
DisplayLCD
Power SupplyRechargeable Battery
Measurement TypeDensity and Moisture
Radiation SourceCesium-137 and Americium-241
ApplicationSoil
Depth of MeasurementUp to 12 inches (300 mm)
Measurement Time1 minute (standard)
Battery LifeApproximately 8 hours
Operating Temperature14°F to 122°F (-10°C to 50°C)