Vertiv | Liebert PEX4 | User Manual 18
Installation
2.2.3. Maintenance Space Requirement
When installing the unit, a minimum maintenance space of 900 mm must be reserved in-front of the air
conditioner unit. The requirement for maintenance space is given in Figure 2-7.
Figure 2-7 Maintenance Space of Unit
Normal maintenance space requirements are given in Table 2-1.
Table 2-1 Normal Maintenance Space (unit: mm/inch)
Space Location Air Cooled Series
Front
mm inch
900 35.4”
The given space parameters are used to provide regular maintenance, such as changing the air lter,
adjusting the supply of the unit, cleaning the humidier and so on.