Installation
2.8.11. Electrical Installation Inspection
After the electrical installation is completed, conrm the following points as given in the following Table 2-17.
Table 2-17 Installation Inspection Checklist
Items Results
The power supply voltage meets the rated voltage on the unit nameplate.
The system electric loop has no open circuit or short circuit.
Power cables and ground cables to the MCBs, indoor unit and outdoor unit are well
connected.
The ratings of the MCBs and fuses are correct.
The control cables are well connected.
All the cables connections are fastened, with no loose screws.

Table of Contents

Questions and Answers:

Question and Answer IconNeed help?

Do you have a question about the Vertiv Liebert PEX4 Series and is the answer not in the manual?

Vertiv Liebert PEX4 Series Specifications

General IconGeneral
BrandVertiv
ModelLiebert PEX4 Series
CategoryAir Conditioner
LanguageEnglish

Related product manuals