7.5.2. Zero Air Part
Install compressed air with a ¼” tubing to AIR IN. The air quality must meet the minimum specication
according ISO8573-1:2010 Class 1.2.1. The pressure must be between 4.5 to 10 bar (65 to 160 psig).
The AIR OUT is a 1/8” Swagelok connector.
7.6. INITIAL START-UP
7.6.1. Filling the Water Tank
The water tank is external. Fill the tank with distilled or deionized water. The conductivity of the water used in
the generator must not exceed 2µS/cm.
CAUTION: To prevent
contamination of the cell
assembly, it is important to use
only deionized or distilled water
in the generator.