Quick installation and start-up flowchart
Task See
Plan the electrical installation and acquire
the accessories needed (cables, fuses,
etc.).
Check the ratings, required cooling air
flow, input power connection,
compatibility of the motor, motor
connection, and other technical data.
Planning the electrical installation
(page 43)
Technical data (page 119)
Check the installation site. Requirements for the installation site
(page 27)
Unpack and check the units (only intact
units may be started up).
Check that all necessary optional
modules and equipment are present and
correct.
Mount the drive.
Checking the delivery (page 28).
Mounting and cooling (page 29).
Route the cables. Routing the cables (page 39)
Check the insulation of the supply cable,
the motor and the motor cable.
Checking the insulation of the assembly
(page 44)
Connect the power cable.
Connect the motor cable.
Connect the control cables.
Connecting the power cables (page 45).
Motor connections (page 52).
Electrical installation: input / output
(page 59).
Check the installation. Installation checklist (page 87).
Start the drive. Start-up (page 89)