92 System Manual SCK Gas Sampling System 42/23-81 EN Rev. 4
Overview: installation
This section contains a list of tasks to be performed when installing the gas sam-
pling system. Links are given to the specific installation instructions describing
installation of the various modules in detail.
It is recommended to have initial startup of the gas sampling system performed by
the manufacturer's trained personnel or by the supplier.
In order to be able to install the various modules of the gas sampling system, prep-
arations must be made at the cement works. A list of preparatory tasks is given in
the "Engineering Guideline".
The rotary kiln must be shut down during installation of the wall tube. Installation of
the gas sampling system should also preferably be performed while the kiln is shut
down. If installation is performed while the kiln is operating, personnel must always
wear adequate heat-proof clothing during assembly of the probe retractor (uncov-
ered duct opening!).
Proceed as follows to install the complete system:
Step Procedure Instructions in ...
1
Check place of installation
of the various modules of
the gas sampling system.
Checking site conditions on
page 93
2
Install the probe retractor
such that personnel are not
endangered and the system
cannot be damaged.
Installing the probe retractor
on page 95
3
Install control cabinet in
suitable place.
Installing the control cabinet on
page 98
4
Install compressed-air
supply, install compressed-
air tank if necessary.
Installing the compressed-air
supply on page 99
5
Install cooling module. Installing the cooling module
on page 101
6
Lay and connect cooling
water hoses.
Installing the cooling water
circuit on page 103
7
Connect external sample
gas line to retractor.
Connecting the sample gas
line to the retractor on page
104
8
Connect electric lines. Connecting internal electric
cables on page 105
9
Connect external electric
cables.
Connecting external electric
cables on page 107