4 Transport / Commissioning
BNNbOO
ID: 1138310 Issue date January 01, 2010
36
Commissioning
The machine as delivered is essentially ready for operation. Observe the
following before commissioning:
• Familiarize yourself with the manual.
• Perform ten-operating-hours maintenance. This procedure is described in
the "Maintenance" section.
• Make sure that the joint protection is open.
Roller with pneumatic wheel (combined roller)
• If using a combined roller, you must check tire pressure and adjust as
required. The ex works pressure is set to 2.5 bar.
• Tire pressure must be adjusted to suit the compaction condition of the
ground:
Tire pressure too low Tire pressure OK Tire pressure too high
NOTE
The tires must be replaced if the fabric is visible on the tire surface.