3A.7 INSTALLATION CHECKLIST:
The mechanical and electrical installation must be checked before start-up.
MECHANICAL INSTALLATION CHECKLIST
Ambient temperature and humidity within specifications.
Unit mounted properly on a vertical, non-flammable surface.
Cooling path not obstructed.
ELECTRICAL INSTALLATION CHECKLIST
Drive properly grounded.
Mains voltage matches nominal input voltage of frequency converter drive.
Mains connections properly:
Routed
Tightened
Input connections properly:
Routed
Tightened
Control connections properly:
Routed
Tightened
Appropriate input fuses installed.
No output compensation capacitors in motor connections.
No tools or other foreign objects remaining inside the enclosure.