Sync Pre-Installation 13
Sync Scoring Installation Schedule
IMPORTANT: The following is based on a typical 24 lane center. Schedules may vary
depending on center conguration and product to be installed.
CUSTOMER RESPONSIBILITY
NOTE: Allpreworkmustbecompletedpriortoequipmentarrival.ThisincludesControlDesk
assemblyandinstallation.
1. Site Survey to be performed by a Brunswick Field Engineer. The Field Engineer will need
to meet with the center manager/proprietor, mechanic, electrician, and architect to cover the
following:
a. Determine non-bowling hours.
b. Provide a copy of league schedules.
c. Review electrical system needs.
d. Review overhead structure needs.
e. Review control desk and back ofce congurations.
f. Review Pre-Installation manual.
2. Prepare bowlers area for consoles:
a. Trenching for using electrical conduit.
b. Dual console risers for existing scorer replacement or surface molding.
c. Any tile work or carpeting.
3. Prepare control desk and ofce areas for routing of interconnecting cables.
4. Electrician installs electrical system, sub panels, outlets, surge suppressors, and switches for
Tel-E-Foul units.
5. Install overhead monitor support structure.
6. Center to have a storage area ready for arrival of new equipment.
7. Brunswick receives credit approval.
IMPORTANT: An installation will not be scheduled until credit is approved and structural
certicates are received.
8. Brunswick receives structural certication from bowling center.