Sync Pre-Installation 13
Sync Scoring Installation Schedule
IMPORTANT: The following is based on a typical 24 lane center. Schedules may vary
depending on center conguration and product to be installed.
CUSTOMER RESPONSIBILITY
NOTE: Allpreworkmustbecompletedpriortoequipmentarrival.ThisincludesControlDesk
assemblyandinstallation.
1. Site Survey to be performed by a Brunswick Field Engineer. The Field Engineer will need
to meet with the center manager/proprietor, mechanic, electrician, and architect to cover the
following:
a. Determine non-bowling hours.
b. Provide a copy of league schedules.
c. Review electrical system needs.
d. Review overhead structure needs.
e. Review control desk and back ofce congurations.
f. Review Pre-Installation manual.
2. Prepare bowlers area for consoles:
a. Trenching for using electrical conduit.
b. Dual console risers for existing scorer replacement or surface molding.
c. Any tile work or carpeting.
3. Prepare control desk and ofce areas for routing of interconnecting cables.
4. Electrician installs electrical system, sub panels, outlets, surge suppressors, and switches for
Tel-E-Foul units.
5. Install overhead monitor support structure.
6. Center to have a storage area ready for arrival of new equipment.
7. Brunswick receives credit approval.
IMPORTANT: An installation will not be scheduled until credit is approved and structural
certicates are received.
8. Brunswick receives structural certication from bowling center.