14 Sync Pre-Installation
INSTALLATION SCHEDULE
IMPORTANT: Brunswick installation completion will be delayed if Brunswick pre-
installation requirements are not met.
To Be Performed By Certied Field Mechanic
Day 1
a. Travel to installation.
b. Unload truck and unpack equipment.
Days 2 and 3
a. Layout and routing of cables from scorer console to pinsetter area.
Day 4
a. Continue layout and routing of cables.
b. Mount equipment on curtain wall.
Days 5 and 6
a. Modify pinsetters.
Day 7
a. Route cables in back ofce and control desk areas.
Days 8, 9 and 10
a. Install Sync consoles, overheads, and associated cabling.
To Be Performed By Brunswick Field Engineer
Day 8
a. Travel to installation.
b. Power audit of electronic equipment.
c. Install control desk and back ofce computer systems.
Day 9
a. Continue setup of control desk.
b. Hook-up consoles and overheads.
Day 10
a. Continue console and overhead hook-up.
b. Begin setup of cameras and verify scoring.
NOTE: Somelanesavailableforuse.Possibleleaguecoverage.
Day 11
a. Continue setup of cameras and verify scoring.
b. Adjust consoles and overheads.
c. Cover leagues and open bowling.
Day 12
a. Complete system checkup and go over spare parts kits.