12.4.2 Protective Equipment during Installation
During the installation the following protective equipment must be worn, to prevent possible injuries in the
respective work steps:
Installation: Safety shoes
12.4.3 Protective Equipment during Operation
No protective equipment is required during the operation.
12.4.4 Protective Equipment during Disposal / Deinstallation
During the deinstallation and disposal the following protective equipment must be worn, to prevent possible injuries
in the respective work steps:
Deinstallation: Safety shoes
Disposal: Safety shoes
12.5 Preparation of the ICS for Use
12.5.1 Installation Information
The electrical, mechanical and thermal integration of the CPM is to be ensured by the vehicle manufacturer. This is
described in chapter 12.7.2. The manufacturer is not liable for damage, that results from the faulty integration of
the CPM in the target vehicle of the vehicle manufacturer.
12.5.2 Placement of the GPM
The GPM is placed flat and level on the ground. Rubber feet underneath the GPM prevent the GPM from shifting
on the support surface. Optionally the GPM can be fixed on mounting rails, see 12.5.4 Optional Installation of the
GPM with Mounting Rails.
12.5.3 Alignment of GPM to CPM
For the alignment of the GPM to the CPM, refer to Figure 12. The vehicle manufacturer is responsible for the
provision of the correct dimensions for the installation of the GPM in the charging station. For the position of the
GPM in the charging station the dimensions of the vehicle must be taken into consideration. For damage that is
due to faulty installation of the GPM in the charging station, no liability is accepted on the part of the manufacturer.
Operation Manual
Inductive Charging System
ICS115