Send document comments to nexus7k-docfeedback@cisco.com
9-35
Cisco Nexus 7000 Series Hardware Installation and Reference Guide
OL-23069-06
Chapter 9 Replacement Procedures
Replacing a Cisco Nexus 7010 or 7018 Fabric Module During Operations
Figure 9-14 Packing a Cisco Nexus 7010 Fabric Module (N7K-C7010-FAB-1)
1 Open the box. 6 Place the foam padding on top of the module.
2 Place the foam padding on the bottom. 7 Fold the narrow flaps over the top of the box.
3 Place the foam padding with the middle cut
out on top of the foam padding in the box.
8 Fold the wide flaps over the top of the box.
4 Place the trifold piece of cardboard inside the
hole in the foam padding.
9 Tape the wide flaps together and to the box.
5 Put the fabric module in an ESD bag (not
shown) and then place the bagged module in
the hole of the padding.