3-16 l In sta ll ation
Testing the Installation (continued)
5 Turn ON the hopper and machine loader switches.
• The conveying blowers should turn on and the LEDs will turn off
and on.
6 Turn OFF the rocker switches for the hopper and machine loaders.
7 Press the STOP button.
• The blowers will continue running as needed to cool the heaters
(until both heaters are less than 150°F {66ºC})
8 The test is over. If the dryer performed the normal operating sequences as out-
lined, you can load the hopper and begin operation. If it did not, refer to the
Troubleshooting section of the User Guide.
Using Communications (Optional)
To use the optional Modbus, Ethernet, SPI or standard Devicenet communica-
tions, see the Addendum for hardware installation and configuration.
DeviceNet connection
SPI connection
Ethernet connection