Machine Loader Conveying
1 Move the MDCW to the processing machine. Lock the wheels and connect
the main power source. Connect the water source if you have an aftercooler.
Connect compressed air if the self-loading option is being used.
2 Mount the vacuum receiver on the feed throat. Push the vacuum receiver
onto the mounting bracket.
3 Place the appropriate material
insert inside the distribution box.
4 Make sure all hoses are connected
securely.
5 Adjust the demand sensor. Position the sensor at the lowest
level of material that you want to maintain in the viewing
chamber before another load cycle begins. Make sure the
sensor rests against the sight glass.
6 Set the load time. See page 4-12, Screen 6
7 Start conveying. Turn the “machine loader” switch ON.
2
3
1” opening
Virgin material insert
Regrind material insert
1.25” opening
4-40 l Operati on