PRELIMINARY CHECKS
A. PRE-DELIVERY CHECKLIST
Carefully check all measurements of the lift hoistway enclosure and compare to the site
installation drawing. Main items to be checked are:
Items to be checked against site installation drawing Checklist 3
Total travel from the bottom finished floor level to the top finished floor level.
Clearance overhead. Top finished floor sill to top of the shaft.
Measure width and depth of hoistway. Check to ensure hoistway is “square.”
Pit depth (check for equal depth and level).
Size and location of the landing door or doors rough openings.
Location of the machine (pump) room.
Location of the electrical power disconnect switches.
Correct voltage, three phase or single and the proper size of the feeder
(assure compliance with local codes).
Ensure the jack unit can be placed in the shaft (clear access to
shaft/runway).
Review “Provisions by Others” with site supervisor.
Check that all walls/barriers surrounding hoistway area are smooth, solid,
vertical and perpendicular to the floor and walls are square to each other.
NOTE: It is important walls are perfectly level due to tight running
clearances.
Check oil and electrical line “sleeves” from machine room to hoistway.
Confirm rail support wall is properly installed as per appropriate drawing.
B. PRE-INSTALLATION CHECK
We strongly recommend that you conduct a before installation check when you receive
shipment to verify contents for damaged or missing parts. Uncrate all boxes and spread out
the parts. Carefully check for damages that you must report to your carrier immediately and
check for missing materials against our shipping list.
NOTE
NO CLAIMS FOR SHORTAGE WILL BE ALLOWED UNLESS REPORTED WITHIN 24
HOURS OF RECEIPT OF SHIPMENT.