SiENBE04-808_A
Trial Operation and Field Settings 286
Part 8
Trial Operation and
Field Settings
1. Trial Operation ....................................................................................286
2. Field Settings ......................................................................................288
2.1 Model Type Setting ..............................................................................288
2.2 When 2 Units are Installed in 1 Room..................................................288
2.3 Standby Electricity Saving....................................................................289
2.4 Facility Setting Jumper and Switch
(cooling at low outdoor temperature)....................................................290
2.5 Jumper and Switch Settings.................................................................291
3. Application of Silicon Grease to a Power Transistor and
a Diode Bridge ....................................................................................292
SiENBE04-808_A.pdf 298 21/02/2011 13:20:25