Installing, Removing, and Replacing
file:///T|/htdocs/stor-sys/ML6000/en/html/ch08.htm[9/17/2012 1:50:35 PM]
1 Library control blade (LCB)
2 GB Ethernet port
3 Power supplies
4 Power cords
5 Ethernet cables from LCB to expansion module
6 FC cable from FC I/O blade to tape drive
7 Module terminator
8 FC cable to host
9 Module-to-module cable
10 Ethernet cable to network
11 UPPER and LOWER Ethernet ports
Required tools: None
1 If your library is 14U or larger, install it in a rack. See Installing the Library in a Rack for instructions. The instructions
include procedures for removing and replacing tape drives.
Warning: All libraries taller than 14U must be installed in a rack having a main protective earthing
(grounding) terminal, and power must be supplied via an industrial plug and socket-outlet and/or an
appliance coupler complying with IEC 60309 (or an equivalent national standard) and having a protective
earth (ground) conductor with a cross sectional area of at least 1.5 mm
2
(14 AWG).
To ensure proper airflow and access space, Allow 60 cm (24 inches) in the front and back of the library.