Operation Overview - 62 RT45 Operator’s Manual
Planning
Planning
1. Gather information about jobsite. See page 66.
2. Inspect jobsite. See page 67.
3. Classify jobsite. See page 68.
4. Select chain and teeth to match your soil type, if necessary. See page 134.
5. Check supplies and prepare equipment. See page 70.
6. Haul equipment to jobsite. See page 83.
Digging with Backhoe
1. Start unit. See page 72.
2. Set stabilizers and unstow backhoe. See page 88.
3. Excavate. See page 90.
4. Stow backhoe properly. See page 92.
5. Shut down tractor. See page 75.
Trenching
1. Start unit. See page 72.
2. Position tractor and controls. See page 96.
3. Begin trenching. See page 98.
4. Complete the installation. See page 98.
5. Backfill the trench. See page 140.
6. Shut down tractor. See page 75.