Appendix K: System Functional Testing
1) Tank-Level Monitor Functions
a) Confirm Probe reading correct product level: Yes No
b) Print inventory report, measure product level at or near Probe riser and confirm probes reading correctly
:
Yes No
2) Leak-Sensor Functions
a) Sensor Function Tests:
b) Sensor Model(s) 30-0231-S, 30-0230-S, 30-0232-D-10 &30-0232-D-20 &30-0232-D-10B, 30-0232-D-20B:
c) Individually remove sensor from mounting bracket/riser, then place sensor upside down (on sensor models 20-0232-D-XX- remove sensor
from wet monitoring well and leave bottom of sensor in up-right position):
i) All sensors initiate individual alarm on console: Yes No N/A
ii) All sensors indicate alarm on correctly labeled channels: Yes No N/A
iii) All sensors alarms activate appropriate relay on Multi-Relay board: Yes No N/A
d) If sensors utilized for line-leak detection and positive shutoff of pressurized system:
i) All designated sensor alarms activate appropriate relay in Multi-Relay: Yes No N/A
ii) Module and/stops operation to the appropriate submerged pump: Yes No N/A
3) Line Leak Detector Functions
a) 3-GPH shutdown test:
i) Observe Lockout/Tagout procedures and de-energize submerged pump power. Have appropriate approved container and spill-
containment material on hand. Individually install calibrated 3-GPH leak-generating apparatus into each piping system and into approved
container. Re-energize submerged pump power, authorizes and cycles power to submerged pump relay.
b) All test indicates alarm for and shuts down appropriate submerged pump: Yes No N/A
i) Observe Lockout/Tagout procedures and de-energize submerged pump power and have appropriate approved container and spill-
containment material on hand when removing the leak-generating apparatus
4) System Status Tests, History, Setup and Checklist Verification
a) Configuration Report printed and reviewed for proper programming: Yes No
b) Console audible and visual alarm tested and functioning properly: Yes No
c) Print Leak Sensor Status: Review data for “Normal” conditions of sensors.
i) Leak Sensor Status printed and reviewed: Yes No N/A
d) Print TLM Leak Test History Information: Review Leak Test History for proper recording of all applicable leak tests.
i) TLM Leak Test History Printed and Reviewed: Yes No
e) Print Line Leak Test History Information: Review Line Leak Test history for proper recording of all applicable leak tests.
i) Line Leak Test History Printed and Reviewed: Yes No N/A
f) Print System Event History: Review data for alarms, troubles and long period of times that the system power was interrupted and not