Mark each tank where no problem is observed with a checkmark:
If certain equipment is not required and/or not present, mark checklist in the N/A column.
If a defect is found, mark the checklist with an “X,” describe the problem in the “DEFICIENCIES” section and notify the appropriate person.
Soil Vapor
Monitoring
Sensing device calibrated and tested
Groundwater
Monitoring
Sensing device tested
Electronic Line-
Leak Detection
Verify that no line sensors have been disabled and electrically by-passed
Evaluate the leak-test history for information indicating that the system is
successfully performing the desired tests
Evaluate the alarm history for a pattern of leak-test failures or system
problems
3-GPH shutdown test performed
Describe any deficiencies: