5 Installation
Pre-installation inspection
WARNING
Please comply with local safety regulations and operational rules during installation.
Only complete and undamaged equipment can be installed! Please ensure that before
installation:
The product cabinet itself should be complete and intact.
All equipment in the cabinet should be complete and intact.
Installation environment requirements
Site selection requirements:
When selecting the installation site, full consideration should be given to the
surrounding environment (climate and geological conditions, such as stress wave
emission, underground water level, no high cables in the vertical upper part of the
installation site, no pipelines or other underground facilities in the lower part of the
installation site, and a certain safety distance should be maintained between the
equipment and buildings and people, the length of the distance should be subject to
the fire safety regulations of the project).
The surrounding environment should be dry and well ventilated.
Please ensure that there are no trees around the installation location to prevent
branches or leaves from blocking the doors or air inlets of the energy storage
integrated system during strong winds.
The installation location should be away from toxic and harmful gas and flammable,
explosive, corrosive, and dust-intensive materials.
The installation location should be away from residential areas to avoid noise.
Foundation requirements:
The foundation should provide sufficient load-bearing support for the equipment.
The height of the foundation should be higher than the historical highest flood level.
The basic bearing capacity is > 3t/, the Basic service life is > 20 years, and the basic
level is 3mm/.
The product cabinet should be raised to against the rain. The recommended mounting
height of the base is about 300mm-500mm higher than the ground.
Drainage measures should be constructed according to local geological conditions.
Wiring requirements:
According to the positions and dimensions of the inlets and egress point of the cable at
the bottom of the cabinet, sufficient space should be reserved for the AC side cable
trough and the cable guide should be inserted in advance during foundation
construction.
The specifications and quantity of perforated pipes are based on the cable model and
quantity of the cable.