Eaton 93PR 500 kW UPS
User's and Installation Guide
33
3.4. Instruction for Removing the UPM Module Packaging
1. Cut off the packing strap and open the carton;
2. Lift the foam on the UPM module upward to remove them;
3. Take out the UPM module.
NOTE
The UPS is heavy. It requires two people for transportation due to its weight.
NOTE
Check whether the UPS is damaged during the process of transportation or not. Should any damage be observed or parts
be found missing, do not start the machine. Contact the forwarder and distributor immediately.
Figure 3-9: Instruction for Removing the UPM Module Packaging