Chapter 6 UPS OPERATING INSTRUCTIONS
The control panel is used to set up and control the UPS, and to monitor UPS operation. For a description of the UPS control
panel functions, see Section
6.2.
NOTE
• Before starting the UPS, ensure all installation tasks are complete and a preliminary startup has been performed by authorized
service personnel. The preliminary startup verifies all electrical interconnections to ensure the installation was successful and
the system operates properly. Read these instructions and have a thorough understanding of UPS operation before attempting
to operate any of the controls. The UPS is configured to operate with one of following nominal voltages: 380, 400, or 415 Vac.
Before operating the UPS, confirm the UPS nominal voltage and frequency from display by selecting Settings -> Info. If the UPS
need to be operated with another voltage or frequency, contact your closest Eaton office or Eaton authorized partner.
• The UPS in not a measuring device. All displayed measurements are only approximate values.
LPS
Control Panel
Door Latch
LPS
Figure 6-1: UPS Controls and Indicators