Installing Options and Accessories
Eaton
®
Power Xpert
®
9395P-900 UPS Installation and Operation Manual P-164000501—Rev 09 www.eaton.com/powerquality 5-9
5.3 Installing an Optional Remote Monitor Panel II
To install RMP II wiring:
1. Verify the UPS system is turned off and all power sources are removed. See Chapter 7, “UPS Operating
Instructions” for shutdown instructions.
2. Perform the procedure listed in paragraph 5.1.
3. Securely mount the RMP II at the desired location. See Figure 5-12 for mounting hole locations.
4. Remove the ISBM cabinet top right interface conduit landing plate to drill or punch conduit holes (see
Figure 4-16).
5. Reinstall the conduit landing plate.
6. Install conduit between the UPS and RMP II. See Figure 5-12 for RMP II knockout hole location.
7. Install wiring between the UPS and RMP II. See Figure 5-2 and Table 5-1 for the Hot Sync CAN Bridge
Card terminal location and wiring information, and Figure 5-7, Figure 5-8, and Table 5-5 for the RMP II
terminal location and wiring information.
8. Install 120 Vac power wiring from the critical bus to the RMP II. See Figure 5-7, Figure 5-8, and Table 5-5
for the terminal location and wiring information.
9. Close the front door and secure the latch.
10. Restart the UPS. See Chapter 7, “UPS Operating Instructions” for startup instructions
NOTE If mounting to a hollow wall, secure the enclosure to a wood or metal stud within
the wall. Do not use hollow wall anchors.
NOTE When installing signal wiring for CAN card J3 terminals, conduit must be installed
between the device and the UPS cabinet.
NOTE 120 Vac for the RMP II should be supplied from the critical bus by facility planners or
the customer.